StoneRidge Builders
prides itself on their homes - if our customer is happy, we are!
We use a specified building process for all of our homes, and
our standard features offer you more than most other area
builders. Of course, upgrades are always an option, and we're
more than happy to go through the details with you item by item
to make the most of your dream home.
Our Building Credo
StoneRidge Builders approach the entire home planning and
building process as a partnership with you. Whether you choose
to build in one of our neighborhoods or on your own land, we
will work together to fully customize your home. Few things
are more satisfying to a home builder than the satisfaction of
a home owner. When finished we have built more than just a
house, we have helped to create your dream home......where a
lifetime of memories await."
Our Building Process
|
Step |
Approximate Time |
Work
Included |
|
1 |
1 Week |
Prepare Site Clear
land, set stakes locating corners of house. Verify all
setback measurements.
Apply for Permits
Check with township and county for local permit
requirements. Some examples are well and/or septic first.
Check with local county health department. |
|
2 |
1 Week |
Excavation Dig
basement and footings for basement.
Driveway Install
culvert and apply gravel. |
|
3 |
1 - 1.5
Weeks |
Foundation Pour
all footings. Pour / lay foundation walls, waterproof below
grade, underground plumbing, drain stack.
Back fill Allow 3-10
days for foundation to cure. |
|
4 |
1 Week |
Concrete Floors
Prepare compacted base and steel reinforcement. Pour and
finish basement, garage, and concrete floors. Hook up city
water sewer lines. |
|
5 |
3 Weeks |
Frame House Build
& set: floor, walls, and roof system 1) apply shingles
2) install windows and exterior doors 3) install
siding. |
|
6 |
1 Week |
Rough Heating Cut
and install duct work. |
|
7 |
2 Weeks |
Rough Plumbing
Locate plumbing fixtures. Install water and gas lines. Set
tubs and shower units in proper rooms. |
|
8 |
2 Weeks |
Rough Electric
Install meter. Set service panel and connect to meter and
ground. Locate and run wire to all fixtures and outlet
boxes. |
|
9 |
2 Weeks |
Insulation and Drywall
Install insulation first. Hang and finish drywall. |
|
10 |
2 Weeks |
Interior Finish Paint
All walls and ceilings. Install all interior doors and
cabinets. Apply all Interior trims and railings. Set counter
tops and vanities. Finish all doors and trim. |
|
11 |
2 Weeks |
Finish Electric
Install light fixtures, vent fans, doorbells, switches,
plugs and wall plates.
Finish Plumbing
Install toilets, sinks, faucets, etc.
Finish Heating Vents &
grilles. |
|
12 |
2 Weeks |
Install
Flooring Set tile, lay carpet and vinyl.
Final Grade Shape and
grade yard to final design
Final Inspections
County and or township final building inspections. Receive
Certificate of Occupancy. |
|
Complete! |
|
Move In! |
This timetable is only an
estimate. Our goal is to build your home within 4-6 months. It
is based on previous home construction schedules of completion.
Weather conditions, availability of sub-contractors, and site
inspections may alter these time estimates. The actual length of
time it will take you to build your home may vary.
We are required by law to get the necessary permits and have
site inspections and approvals per city or township codes.
Our
Standard Features
All of our homes
include these standard features. Upgrades are available, and we
will be happy to consult with you to determine your preferences.
Click below to view our Standard Features lists:
|